Investment Procedures And Sequences

(Resolution No. 31/QĐ-UBND date 19/7/2017 of the People's Council of Binh Phuoc Province)

Procedure 1: Investment procedure for the project subject to the Decision on investing out of the economic zone, industrial parks and industrial clusters (Projects subject to cases as specified in Clause 1, Article 32 of the Law on Investment)

Processing time is described as follows:

1. As prescribed by the Central: 187 working days.

2. Time for committing reforming the administrative procedures undertaken by the Department of Planning and Investment reduces to: 50 working days.

The specific procedure includes 07 steps as follows:

 


Procedure 2: Investment procedure for the project not subject to the Decision on investing out of the economic zone, industrial parks and industrial clusters

(Projects not subject to cases as specified in the Decision on Investment Guideline under the Procedure 1)

Processing time is described as follows:

1. As prescribed by the Central: 108 working days.

2. Time for committing reforming the administrative procedures undertaken by the Department of Planning and Investment reduces to: 20 working days.

The specific procedure includes 06 steps as follows:

 


Procedure 3. Procedure on fulfilling the investment procedure into Hoa Lu Border Gate Economic Zone

When the valid documents are submitted to the One-Door Division under Economic Zone Authority, Binh Phuoc Province.

Processing time is described as follows:

1. The procedures, sequences and processing time for all administrative procedures for one project is 135 working days; the processing time for each procedure is 50 working days at most and 15 working days at least as prescribed.

2. The fulfillment time in the Economic Zone Authority for each procedure is 10 working days at most and 03 working days at least.

* All steps in the procedure are simultaneously implemented; the maximum processing time is 10 working days (since the written agreement on land assignment and land lease is released).

Concretely:


Procedure 4. Sequences on fulfilling the investment procedures into the industrial parks

When the valid documents are submitted to the One-Door Division under Economic Zone Authority, Binh Phuoc Province.

Processing time is described as follows:

1. The procedures, sequences and processing time for all administrative procedures for one project is 135 working days; the processing time for each procedure is 50 working days at most and 15 working days at least as prescribed.

2. The fulfillment time in the Economic Zone Authority for each procedure is 10 working days at most and 03 working days at least.

* All steps in the procedure are simultaneously conducted; the maximum time is 10 working days.

Concretely: